Assumptions and prerequisites |
- Allowable load of operation floor and passageway : 1.2t/㎡
- Size of equipment which should be transported through passageway : Width 1.2m, Height 3m or less
- Overhead crane specification (Rated load 100t)
- Use existing opening, hatch, and stairs inside the reactor building for accessing each floor and delivering the equipment to each floor. No new openings, in principle, shall be created on the outer wall of the building. (Seismic resistance and leakage prevention of radioactive materials shall be considered when creating new openings.)
- Total weight of equipment installed on the operation floor shall be minimized in consideration of seismic safety.
|