Task(s): Method for removing PCV/RPV upper head, considering deformation and dose rate increase.
(4) Remove PCV/RPV upper head - Major challenges on the actual method
Removal
- Method for removing PCV/RPV upper head considering deformation, and sticking and biting of PCV/RPV upper head
- Management of the dose rate increase when removing PCV/RPV upper head
- Preparation of temporary storage
- Method for transportation of PCV/RPV upper head to the temporary storage
- Method for temporary placement of PCV/RPV upper head
- Method for transporting removed PCV/RPV upper head to another temporary storage
- Control method of atmospheric environment inside PCV after removing PCV/RPV upper
Prevention of dose rate increment
- Management of the dose rate increase when removing PCV/RPV upper head
Assumptions and prerequisites |
- Air dose rate inside the PCV/RPV
- Dose rate inside the PCV 100Gy/h
- Dose rate inside the RPV 1kGy/h
- Effective dose rate outside the PCV
- Operation floor : 1mSv/h
- Operation areas except for operation floor : 3mSv/h
- Passageway inside the building : 5mSv/h
- Overhead crane specification (Rated load 100t)
|