Task(s): Method for dismantling of internal equipment, transport and storage after dismantling.
(6) Dismantle and remove internal structures - Major challenges on the actual method
Removal
- Method for cutting/dismantling/removing the internal structures
- Equipment to be used for the method
(Out of scope of the cutting and dust collection technology written in the RFP)
- Cooling method when current water cooling system becomes unavailable
Temporary storage
- Preparation of temporary storage
- Method for transportation of the internal structures to the temporary storage
Assumptions and prerequisites |
- Allowable load of operation floor and passageway : 1.2t/㎡
- Size of equipment which should be transported through passageway : Width 1.2m, Height 3m or less
- Overhead crane specification (Rated load 100t)
- Air dose rate inside the PCV/RPV
- Dose rate inside the PCV 100Gy/h
- Dose rate inside the RPV 1kGy/h
|