Task(s): Retrieval method, considering post processes and prevention of dose rate increase.
(3) Remove shield plug - Major challenges on the actual method
Transport / install equipment
- Places to assemble and install equipment for removing shield plug, if necessary
- Equipment to be used for assembly
- Maintenance of equipment and actions to trouble
Assumptions and prerequisites |
- Allowable load of operation floor and passageway : 1.2t/㎡
- Size of equipment which should be transported through passageway : Width 1.2m, Height 3m or less
- Overhead crane specification (Rated load 100t)
- Effective dose rate outside the PCV
- Operation floor : 1mSv/h
- Operation areas except for operation floor : 3mSv/h
- Passageway inside the building : 5mSv/h
|
Removal
- Method for removing shield plug, considering possible deformation, and sticking and biting of the shield plug
- Preparation of temporary storage, and method for temporary placement of the removed shield plug
- Method for transportation of shield plug to the temporary storage
- Method for temporary placement of shield plug
- Method for transporting removed shield plug to another temporary storage
Countermeasures on dose increase
- Management of dose rate increase when removing shield plug
- Consideration of shielding substitutes for the shield plug