Example of method 3 "Retrieving fuel debris from the side”

ⅰ) Challenges and reference information : (7) Collect fuel debris and transfer canisters

Task(s): Method for preparing temporary storage location and transportation of canisters.

(7) Collect fuel debris and Collect fuel debris and transfer canisters - Major challenges on the actual method

(1)Prior preparation (2)Install barrier (3)Create opening on the side of PCV (4) Install equipment and access (5)Dismantle and remove internal structures (6)Retrieve fuel debris
(7)Transport canister (8)Clean-up equipment

Storage method

  • Models of canister to be referred for temporary storage (Ex. Canister used at TMI-2)
  • Setting of installation places for canisters during storing operation
  • Method for storing the cut fuel debris
Plant information

Determination of temporary storage location

  • Assumption of specification of canister
  • Temporary storage for canisters
    (Although basically SFP should be used, other sites can be used when accessing from the side)
Plant information

Transporting method for canister

  • Layout of canisters setting at temporary storage
  • Method for installing canisters safely
  • Method for transferring canisters to temporary storage
  • Necessity of the barrier for canisters
Plant information
Assumptions and prerequisites
  • Allowable load of operation floor and passageway : 1.2t/㎡
  • Size of equipment which should be transported through passageway : Width 1.2m, Height 3m or less
  • Overhead crane specification (Rated load 100t)