Example of method 3 "Retrieving fuel debris from the side”

ⅰ) Challenges and reference information : (5) Dismantle and remove internal structures

Task(s): Method for dismantling of internal equipment, transport and storage after dismantling.

(5) Dismantle and remove internal structures - Major challenges on the actual method

(1)Prior preparation (2)Install barrier (3)Create opening on the side of PCV (4) Install equipment and access (5)Dismantle and remove internal structures (6)Retrieve fuel debris
(7)Transport canister (8)Clean-up equipment

Removal

  • Method for cutting/dismantling/removing the internal structures
  • Equipment to be used for the method
    (Out of scope of the cutting and dust collection technology written in the RFP)
Plant information
Assumptions and prerequisites
  • PCV/RPV interior air dose rate
    - PCV interior dose rate 100Gy/h
    - RPV interior dose rate 1kGy/h

Temporary storage

  • Preparation of temporary storage
  • Method for transportation of the internal structures to the temporary storage
Plant information
Assumptions and prerequisites
  • Allowable load of 1st. floor : 1.2t/㎡
  • Size of equipment which should be transported through passageway : Width 1.2m, Height 3m or less