(1) Prior preparation
- Seismic assessment when creating opening on the building for investigation and fuel debris retrieval
(2) Install barrier
- Seismic assessment of barrier equipment
- Seismic assessment of building when installing barrier on the operation floor
(3) Remove shield plug
(4) Remove PCV/RPV upper head
(5) Install equipment and access
- Seismic assessment of equipment for fuel debris retrieval
- Seismic assessment for the building when installing equipment on the operation floor
(including shielding equipment)
(6) Dismantle and remove internal structures
- Seismic assessment of equipment for retrieving fuel debris
- Structural stability of internal structures during dismantling of internal structures
(7) Retrieve fuel debris
(8) Collect fuel debris and Transfer canisters
(9) Clean-up equipment
Assumptions and prerequisites |
- Allowable load of operation floor and passageway : 1.2t/㎡
- Size of equipment which should be transported through passageway : Width 1.2m, Height 3m or less
- Total weight of equipment installed on the operation floor shall be minimized based on seismic safety.
|